All Collections
Maintenance
Planned maintenance
How the due date is calculated when the planned maintenance is based on running hour recurrence?
How the due date is calculated when the planned maintenance is based on running hour recurrence?

Find out how the due date is calculated when choosing a running hour recurrence.

Guireg CAPITAINE avatar
Written by Guireg CAPITAINE
Updated over a week ago

When you create your planned tasks, you have to choose between a calendar recurrence or a running hours recurrence.

👉 If you choose the calendar recurrence, the due date will be displayed.

👉 If you choose the running hours recurrence, an estimated due date will be calculated.

So how is it calculated? 🤔

This is how it works:

  • The average number of walking hours per day = (latest meter value-initial meter value) / (difference in days between the last meter date and the initial meter date).

  • The remaining days between the current meter and the due date = (meter value for the maintenance deadline - the current value) / average number of walking hours per day.

  • Estimated next due date = Latest reading date + Remaining days between the current meter and the due date.

Did this answer your question?